Scotia Camp

Wandoan, Queensland Design and Construct
Client Santos
Duration October, 2016 - February, 2017 (construction)
Status Completed
Capacity 300 Beds

The FKG Group’s Accommodation Facilities and Camps team, now operating as Anaman, was engaged by Santos to deliver a 300-bed workers camp to support their operations in Wandoan.

To meet the client’s needs, two existing camps were demobilised and transported to site by truck. The relocation included 126 modular buildings, a wet mess, gym, kitchen, theatre, and accommodation blocks.

All associated civil works were also undertaken, including the preparation of building pads and carparks, with electrical services delivered by FKG Group service partner NRG Services.

With such a short project delivery time required, the team worked on a continuous roster to meet the timeline. Also assisting to reduce the program, a 100T crawler crane was used on site.

Value Adds

  • Dismantling and relocation of all buildings and infrastructure, including sewage treatment and power generation systems
  • Delivery of a fully functional, pre-commissioned camp
  • To improve occupant comfort, all of the mattresses were replaced; and previous mattresses were donated to a not-for-profit organisation, organised through a client contact.